Finishing the work leaves a homeowners’ association with another job: showing the Generalitat what was completed and paid for. For buildings awarded a Next Generation renovation grant under the 2024–2026 call, an award does not replace the application for final approval and payment.
As of 18 November 2026, procedure GVA 96365 is closed to new applications: that window ended on 27 February. Existing files can still receive corrections and supporting evidence. This guide is for those already handling a building grant, rather than an announcement of open funding for a lift or home improvements.
Start with three dates
Find the award decision, the authorised deadline for completing the work and the notification date. The electronic office shows its evidence submission stage available until 30 September 2028. That general platform closing date does not replace the deadline applying to your file.
The procedure states that final approval and payment must be requested within three months after the maximum authorised period for carrying out the work ends. If work was completed before the grant was awarded, the three months run from notification of the award. Ask the person managing the file to record which situation applies to your association.
The evidence and invoices must describe the same work
- Find the file number and the final approval and payment form for the 2024–26 call.
- Gather the as-built project where applicable, start and completion certificates, the heating installation certificate if required, and the registered post-work energy certificate produced with the same software as the original assessment.
- Ask the qualified professional for the report confirming compliance with the grant conditions. Include colour photographs, necessary permits and the declaration of regulatory compliance.
- Prepare certified lists and copies of orders or contracts, invoices and bank payment records, together with the declaration of other grants and any additional applicable documents.
A renovation manager or agent must submit electronically. In the official procedure’s evidence submission stage, the applicant identifies themselves, enters the beneficiary and file details, attaches the documents and registers the submission. Keep the receipt: files saved on a computer have not been submitted.
Check approval if the project changed
Order 3/2026 requires immediate notification of changes that could affect entitlement. Exceptional amendments require reasons and must meet conditions; notifying a change does not establish approval. Extensions of completion and evidence deadlines through the bilateral commission are exceptional and conditional, rather than a general entitlement.
If final eligible expenditure falls below the original estimate, the Generalitat recalculates the grant and may reduce it. Higher costs do not increase the award. Before settling the association’s accounts, reconcile the grant awarded, the expenditure supported by evidence and any authorised amendments.
Sources and procedure: GVA 96365 · DOGV · 3/2026.