At a sales office, “provisional approval” can sound like a formality that is out of the way. The Generalitat has assessed the plans at that stage. Final approval concerns the finished building. If you are considering a protected home off-plan in the Valencian Community, ask the developer for the decision it already holds and check that it covers the development you are being offered.
Before paying an advance
The developer applies for provisional approval with documents including the initial plans, evidence of its rights over the site and a planning certificate from the local council. The decision brings the development into the protected housing scheme on a temporary and conditional basis. If the developer asks for an advance, ask to see the relevant authorisation as well. The Generalitat lists that authorisation separately from the approval itself.
Once the building is finished
To obtain final approval, the developer submits documents including plans showing what was actually built, the municipal building permit and the completion certificate. The housing department may inspect the building and require defects to be put right. The Generalitat sends its decision to the developer and to buyers or people receiving a transfer. Its procedure page says the application is treated as refused if three months pass without an express decision.
If the home was built years ago
Look for the final approval date and the case number in the deed. Decree 180/2024 distinguishes expiry at the end of the protection period from an administrative decision to remove protection. Homes governed by that decree cannot be removed from protection at the owner’s request. The length of protection depends on the applicable rules, and in some cases it is permanent. Use the property’s details to ask the Generalitat to confirm its status through the protected housing information service before agreeing a sale.